Monthly update for Sellers Auto / Artist Studio petroleum cleanup site 489201547 / 489201548 update #60)‏

Damon:
Thanks as always Damon for your monthly report.
Great news you and the cleanup team have achieved the long-term goals of this project and are nearing the final stages!
We’ve sincerely appreciated the reports with updates and milestone achievements all along these past 60 months.
No problem on going to quarterly reports.
We appreciate your commitment and support keeping Lake Formosa Neighborhood informed.
Best regards,
Louise Mills


From: Damon.Taylor@ocfl.net [mailto:Damon.Taylor@ocfl.net]
Sent: Tuesday, November 01, 2011 4:05 PM
To: Mills, Louise (E S SF RNA FSF 7 1)
Cc: JRWebster@r-kidproperties.com; keder@argusconsulting.com; nevans@tempaco.com; Carlos.Gonzalez2@ocfl.net; Renee.Parker@ocfl.net; rhorton3@cfl.rr.com; gspears@lotspeichandassociates.com; e_eade@hotmail.com; jmwordsmithy@gmail.com; ivanhoevillagems@gmail.com
Subject: Monthly update for Sellers Auto / Artist Studio petroleum cleanup site 489201547 / 489201548 update #60)

November 1, 2011

Ms. Mills,

I would like to take this opportunity to give you our sixtieth monthly update on the project.   

We got the final report today that details the operation and maintenance of the system for the last period of operation.  This report also provides Argus recommendation for Post Active Remediation Monitoring (PARM), which we intend to approve. In the next few weeks, we will send our review letter to Argus and approve a quarterly PARM plan for them to get started on monitoring.   All of the milestone wells are below target levels.  Monitoring well DW-11 had on constituent above target levels when it was last sampled on September 27, 2011, which was Benzene at 9.7 µg/L.   This well will be part of the quarterly monitoring and is expected to attenuate.  One idea we are considering is to overpurge this well or to replace this well with a new well adjacent to it. 

I propose that I provide updates on a quarterly basis from now on the contractor will only be coming to sample the wells on a quarterly basis.  Please let me know if you would prefer more frequent updates and I will be happy to give them.  Otherwise, below are the tentative dates for the next four updates:

Ø       February 1, 2012 

Ø       May 1, 2012

Ø       August 1, 2012

Ø       November 1, 2012

 As always, please feel free to call me anytime if you need additional information or have any questions.

Thank you,

Damon Taylor

Environmental Case Manager

Environmental Protection Division

Petroleum Cleanup

800 Mercy Drive, Suite 4

Orlando, FL 32808

office:   407-836-1480

fax:  407-836-1417

email:  damon.taylor@ocfl.net

web:  www.ocepd.org

Advertisements

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s